Case Study

Efficient hot water supply through cogeneration in high-performance sports facilities.

Hot Air icon

Electricity

Electricity generation

Hot Air icon

Hot water

Hot water

CONSUMPTION
539,643 (100%)
GENERATION
532,713 (98.71%)
DEMAND
150kw (100%)
INVOICED DEMAND AVOIDED
75kw (50%)

INSTALLED EQUIPMENT

1 Microturbina C65

FUEL

Gas natural

RESULTS

Electricity demand covered: 150 MWh

Description

In 2021, a Sports Park together with DTC Soluciones took a step towards sustainability and energy efficiency by integrating a distributed generation system with natural gas, designed to cover the thermal demand of the complex through hot water for restrooms, showers and hydrotherapy areas.

A 65 kW natural gas-fired power generation unit was installed, designed to operate in parallel with the grid and recover the waste heat generated during electricity production. This heat was used to heat water for general use, with outstanding thermal efficiency.